Hi, been reading these forums sporadically to up my knowledge of the plumbing industry but right now I am stuck. I currently have a toilet in an upstairs bathroom. It was leaking so I pulled the toilet. Previous homeowner had a rigged together aluminum spout connecting to the waste pipe. My problem is the waste pipe is coming in at about a 20 degree angle to the hole for the toilet. I have put a 22 degree elbow at the end of the run and this is the result. Please see attachment. The elbow was sitting 2.5 inches high so I cut it down. However I do not know how to finish this install. If I add a closet flange I will be up by approximately 2 inches. Any suggestions to solve this issue? As well I am slightly offset within the hole. I cannot modify this because of the joist below. P's sorry for the upside down picture.
On another note what are thoughts on cracks of base of toilet? Replace or no?
On another note what are thoughts on cracks of base of toilet? Replace or no?