Basement plumbing

Plumbing Forums

Help Support Plumbing Forums:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.

Brunstown

New Member
Joined
Apr 5, 2019
Messages
4
Reaction score
0
Location
Alabama
C07F1A97-4F8A-436A-9CA3-C09CD08BEC90.jpeg Everything in red is existing. I plan to wet vent from the new 3” Vent. That wet vent would end at the toilet prior to the existing 1.5” vent, which is connected to the drain via a 3x3x3 wye and hub, which is inline with the proposed new plumbing upstream and existing plumbing downstream. Would it be to correct to increase the 1.5” Vent size and start a new wet vent for the remaining fixtures downstream? So it would be essentially 2 inline wet vents. IPC code here
 
Thank you for the quick response. I’m not sure I follow exactly. Are you suggesting to vent the toilet into the 1.5” (which would be changed to 2”)?
 
5FE264FD-D758-4D5D-B2F3-551E5E88AB5C.jpeg
I hope I’m interpreting this correctly. Option 3 would be ideal. By venting the wc into the 1.5”(changed to 2”)solves my problem with the wc not being the last fixture on the wet vent?
 
08F3CD63-6E9F-4849-8191-D12325AF8C08.jpeg
Hey Frodo, this is all that currently exists in that section. The vent is inline with the drain. E70B1CA9-942E-4E15-B42B-C6725741AA3B.jpeg
Is this how the toilet in the new location should tie in?
 