Revising this drain line to remove two 90-Ells in a row at top.
This is 1.5" PVC coming down from kitchen sink
Would be easiest if I used a 45 ELL - or- should I use a Tee with cleanout as previous
Per code -- Changes of direction.
This is 1.5" PVC coming down from kitchen sink
Would be easiest if I used a 45 ELL - or- should I use a Tee with cleanout as previous
Per code -- Changes of direction.
- Cleanouts shall be installed at each change of direction greater than 45 degrees in the building sewer, building drain and horizontal waste or soil lines.
- Where more than one change of direction occurs in a run of piping, only one cleanout shall be required for each 40 feet developed length of the drainage piping.