Old 01-10-2012, 09:37 PM   #11
Junior Member
 
Join Date: Sep 2011
Location: Bozeman, MT
Posts: 14
Default

Hello, i'm excited to report that I made progress on this project. I actually had a master plumber called in who was willing to give me directions in person. I've come a long ways since then and hope to satisfy all the mechanic requirements for this to work.

Notice: I haven't actually connected the vent pipe to the existing vent in anticipation of direction/criticism from the users here.

Here's a link to the current picture:
click to open

I want to thank everyone again for their great help and excellent advise!


Last edited by snucky; 01-10-2012 at 09:37 PM. Reason: inserted picture was way too large
snucky is offline   Reply With Quote
Old 01-10-2012, 10:12 PM   #12
Moderator
 
Join Date: Jan 2010
Location: Orlando, FL
Posts: 2,270
Default

Please note that codes vary with regions, so what is allowed in one area might not be allowed in another, and vice versa.

You are on the right track. Both fixtures are now vented. The problem is that the vent runs horizontal underneath the rim of the fixtures. Both of the 1/4 bends (90 degree fittings) on the vent need to be removed. Use 1/8 bends (45 degree fittings) to turn both vents back up inside of the wall. At least 6" above the rim of the highest fixture tie the vents back into the existing vent stack.
__________________
Lake County, Florida plumber
Springtime Plumbing Services, LLC
License #11067533
352-630-5673
phishfood is online now   Reply With Quote
Old 01-10-2012, 10:15 PM   #13
Senior Member
 
johnjh2o's Avatar
 
Join Date: Jul 2011
Location: , Florida, East-Central
Posts: 1,089
Default

I don't know where to start. You can not run a vent horizontally below the flood rim of the fixture. Both the toilet and the tub vent should enter the wall then tie in together at 42" above the floor. The tub drain should drop directly into the trap without the two ell's after the trap. Sorry but I hate to say it the master plumber that gave you direction has no idea how to lay out a plumbing system. Did he actually see the finish product?

John
johnjh2o is offline   Reply With Quote
Old 01-10-2012, 10:18 PM   #14
Senior Member
 
johnjh2o's Avatar
 
Join Date: Jul 2011
Location: , Florida, East-Central
Posts: 1,089
Default

phishfood , you did it again you beat me by three min. Do you have a opening in your company for the master plumber that designed his system?

John

Last edited by johnjh2o; 01-10-2012 at 10:40 PM.
johnjh2o is offline   Reply With Quote
Old 01-11-2012, 02:09 AM   #15
Junior Member
 
Join Date: Sep 2011
Location: Bozeman, MT
Posts: 14
Default

wow, you guys, thanks for your amazing help. I take this - hopefully final - mistake on me. The master plumber who gave me directions hasn't seen this yet. He probably mentioned the flood rim and I didn't get it.

Okay, so here's my 4th attempt. I really hope that this will work out. Note:
- the Sani-Tees aren't connected to the vent stack yet b/c I want to make sure i got this right b4 i cut into it
- there absolutely no horizontal runs in the vent pipes anymore up until 50" above the floor

Here's the image (click to see a large version):
snucky is offline   Reply With Quote
Old 01-11-2012, 11:07 PM   #16
Senior Member
 
Join Date: Apr 2011
Location: , Alberta
Posts: 743
Default

ohh, wow.... you could effectively vent thousands of DFU's .. no joke.

Its funny for me to say it but the 90 on the #" horizontal portion of the bathtub vent is technically wrong, though I would be a gazillion dollars it doesnt clog. also "technically" you should have access to cleanouts if a vent is below flood rim, It must be piped as though it were a drain, And again.. must come off of the pipe whos trap it serves ABOVE THE HORIZONTAL CENTERLINE which, technically is impossiblle since you used 3" to vent.

you could have used 2" to achieve the same. how it is I would consider Trap evaporation my biggest concern... It will work, but is way overkill.


Edit:..... hmmm it is 2" isnt it ?? lol, my bad. you're good to go, change out the 90's for 45's add a barett C/o on each vent line and cover them with panels when you finish the wall.

Last edited by LiQuId; 01-11-2012 at 11:14 PM.
LiQuId is offline   Reply With Quote
Old 01-12-2012, 12:38 AM   #17
Junior Member
 
Join Date: Sep 2011
Location: Bozeman, MT
Posts: 14
Default

Hi LiQuId,

I'm excited to be the recipient of good news! This, I have to admit, was beyond me and a frustrating process. But I am glad to not have given up.

The two 90's on the tub vent were the only way possible for me to stay within the wall cavity (I am planning on framing a wall parallel to the existing one just for the tub of about 4" thickness). It's not really a horizontal run as its got a significant slope to it. Still, you're saying that I should replace the 90's?
snucky is offline   Reply With Quote
Old 01-12-2012, 10:27 PM   #18
Senior Member
 
Join Date: Apr 2011
Location: , Alberta
Posts: 743
Default

they are supposed to be following the drainage rules since they are below flood rim, any 90s must be changed to 2 45's ( this makes the transition smoother and more laminar thus eliminating the chance for clogs ) and should be euiped with line cleanouts to cleanout the sections below flood rim as these could fill and drain and over time become clogged and require cleaning, and they are supposed to come off above the horizontal centerline of the branch piping, this is so that they remain free of water and can properly serve as vents. this is as code stipulates.

What are you tying the lavatory into ?? I will add that either of these vent runs could have a lav attached to the vertical by means of a t wye, and that you can run the trap arm of that lavatory a maximum of 6 feet ( if plumbed in 1 1/2 ) and a maximum of 135 ' rotation before it is vented.

it looks to be coming along. Know also that the code I speak of is canadian code, and could have variations in your area.. have it inspected, and make sure that you use purple primer and that it is somewhat visablle on the joints as the inspector will be looking for this.

LiQuId is offline   Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are On
Refbacks are On



Latest Threads

Latest Reviews

MCC USA Inc. - CornerWrench

PASCO - Ez On Basket
Strainer - Brushed Nickel

PASCO - EZ On Basket
Strainer - Satin

Rheem - SolPak

Whirlpool - Du1300xtvq


Copyright © Group Builder, Inc - All Rights Reserved
Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO 3.6.0
Network: Flooring Forum - Home DIY Forum - Garage Forum - Painting Forum